Understanding revenue forecasting in Operating

Written By Lauri Eurén

Last updated 13 days ago

Revenue forecasting answers one question: if your team executes the current plan and performance so far continues, what will this project (or a group of projects) earn in total?

This article explains how Operating builds that forecast and how it differs from planned and earned revenue. It also covers what the forecast cutoff date does and how the forecast behaves for each billing type. It is written for anyone who reads project financials: project leads, finance, and leadership.

Three ways Operating measures revenue

Operating tracks revenue from three angles. Keeping them straight is the key to reading any financial report correctly.

  • Planned revenue is what your current plan expects to earn, looking forward across the whole Project. It includes both confirmed and tentative work, and it does not yet know what has actually happened. Where it comes from depends on the billing type:

    • Time-and-materials and capped time-and-materials: the Allocations, as allocation percentage × working hours × billing rate.

    • Fixed-price: the Budget, spread across the timeline by the revenue recognition method. Allocations shape the spread but do not set the total.

    • Retainer: the fee of each retainer period, plus overage for planned hours past the period's included hours.

  • Earned revenue (the actuals) comes from completed work, so it only ever describes the past. How it is calculated depends on the billing type:

    • Time-and-materials and capped time-and-materials: Time entries at their billing rate.

    • Fixed-price: the revenue recognition method.

    • Retainer: the fee of each retainer period, earned across the period's weekdays, plus overage on tracked hours past the included hours.

  • Forecasted revenue is a hybrid — an estimate at completion. It takes earned revenue for the part of the Project that has already happened, then adds planned revenue for the part still to come. It is the best current answer to "what will this Project earn in total?"

Forecasted revenue is not planned revenue. Planned revenue shows only the initial plan. Forecasted revenue replaces the past portion of that plan with what actually happened, so it stays anchored to reality as the Project progresses.

Measure

Built from

Time horizon

Planned revenue

Per-hour: Allocations × rate. Fixed-price: the Budget, distributed by the recognition method

The whole plan, start to finish

Earned revenue (actuals)

Time entries and recognized revenue

Past only

Forecasted revenue

Actuals before the cutoff + plans after it

Past + future, combined

The forecast cutoff date

The forecast cutoff date is the line between "what happened" and "what we expect."

  • Up to and including the cutoff date, the forecast uses actual tracked time and expenses.

  • From the day after the cutoff, it uses planned Allocations.

The default cutoff is the previous day, which gives you "actuals to date, plans from today forward." Your organization can change the default in Settings → Financials → Forecast, for example to the last day of the previous week or month, so that actuals are complete before they count. Every forecast starts from that date. You can pick a different date in the view you are working in:

  • Project Portfolio report: in the toolbar, once you select a forecasted unit.
  • Projects list: in the Display menu.
  • Project Status tab: on each Project's Status tab.

See "Where you'll see forecasting" below.

Confirmed and tentative work in the forecast

Allocations are either confirmed (scheduled work the team is committed to) or tentative (conditional work, such as a deal that has not closed).

  • Only confirmed Allocations feed the forecast.

  • Tentative work is shown alongside the forecast as a separate, greyed-out value. It represents upside if the tentative work materializes, but it does not move the forecast itself.

This is consistent with how fixed-price recognition already treats uncertainty: on a confirmed fixed-price Project, tentative Allocations receive zero recognized revenue, so they never dilute the forecast.

How forecasting works for each billing type

The forecast follows the Project's billing type.

Time-and-materials

Revenue is earned directly from hours worked, with no ceiling. The forecast is a straightforward substitution: actuals before the cutoff, planned hours × rate after it. The total moves up or down directly with how much work is planned.

On the Project's Status tab this appears as a Projected outcome. It shows earned revenue to date plus plans for the rest of the Project. It is compared against the budget so you can see whether you are tracking over or under.

Capped time-and-materials

Like time-and-materials, but total earned revenue cannot exceed the Budget. After the cutoff, planned revenue accumulates period by period until the remaining Budget is used up.

  • Once a Budget is exhausted: every later period forecasts zero revenue, even where work is still planned. Those planned hours are still shown (as time value) so resource planning stays accurate. They just generate no further revenue.
  • Several Budgets: each Budget caps independently. Unused room in one does not roll over into the next.

Fixed-price

The contract value is fixed. How the forecast spreads it depends on the revenue recognition method the fixed-price Project uses:

  • Every method except milestones (weighted by hours and rates, cost-to-cost, evenly by week or month, and Automatic: Based on tracked time, up to the budget amount). Forecasted revenue lands exactly on the Budget. Operating takes the revenue earned before the cutoff and subtracts it from the Budget. It spreads the rest across future periods in line with their planned revenue.
  • When a milestone is completed. The forecast follows the milestones: each open milestone's value on its target date, and any Budget amount that no milestone claims on the Budget's end date. An open milestone whose target date has already passed forecasts nothing, so the total can fall below the Budget. See Milestone-based revenue recognition and invoicing.

For how each method shapes revenue over time, see How revenue recognition works in Operating.

Because the revenue is fixed, the forecast that matters most is cost and margin. The Status tab shows projected profit and margin, which is the fixed revenue minus projected costs, next to your planned profit.

Retainer

Each retainer period has a fee, and the fee is earned whether or not anyone works. After the cutoff, every future retainer period forecasts its full fee, even when nothing is allocated to it.

On top of the fee, confirmed Allocations past the period's included hours forecast as overage at the billing rate, and planned billable expenses forecast at their amount. Before the cutoff, actuals replace the forecast. See How retainers work in Operating.

Non-billable

Revenue is always zero and a forecast is not meaningful. Costs are still tracked for profitability analysis.

Billing type

Revenue cap

How the forecast behaves

Time-and-materials

None

Actuals before the cutoff, plans after

Capped time-and-materials

Budget

Plans capped by remaining Budget; zero once the cap is reached

Fixed-price

Budget

Every method except milestones: remaining Budget spread across future plans; total always equals the contract. Milestones: open milestones on their target dates, and unclaimed Budget on its end date

Retainer

None: the fee is a floor

Each future retainer period forecasts its fee, plus overage from confirmed Allocations past the included hours

Non-billable

N/A

Always zero

For fixed-price Projects recognized Manual: Based on budget progress, weighted by hourly rates or Based on actual vs planned costs (cost-to-cost), the shape of the forecast also follows your organization's forecast method setting. See How to choose a fixed-price forecast method.

Where you'll see forecasting

  • Project Portfolio report. Choose a forecasted unit to see estimates at completion across your Projects. The forecasted units are Forecasted revenue, Forecasted costs, Forecasted gross profit, and Forecasted margin %. The Forecast cutoff date control appears in the toolbar whenever a forecasted unit is selected.

  • Projects list. The Display menu on the Projects list holds a Forecast cutoff date control. It starts at your organization's default cutoff date. These forecast columns use that date: Forecasted revenue, Forecasted costs, Forecasted gross profit, and Forecasted gross profit margin %. The Projects CSV export uses that date too.

  • Project Status tab. Each Project's Status tab shows a forecast summary. For confirmed Projects, per-hour Projects show a Projected outcome against budget, and fixed-price Projects show projected profit and margin. Tentative Projects have no actuals to forecast from yet, so their Status tab instead shows Planned revenue, Planned cost, and Planned profit, marked as tentative.