What is capacity and how is it calculated?

Capacity shows how much of a Person's working time is booked versus available — built from their working hours, adjusted for time off, holidays, and employment dates.

Written By Lauri Eurén

Last updated 13 days ago

Capacity is how much of a Person's working time is available for work, shown as the percentage booked against the percentage available. Operating builds it from each Person's working hours and subtracts the time they can't work. When someone is away, they're not delivering, so capacity reflects that directly for a realistic forecast.

What sets a Person's available hours

A Person's available working time on any given day is resolved in this order:

  1. A day with no working time in the Person's working hours counts as zero. A Person who works on Saturdays has capacity on Saturdays.

  2. Outside employment dates (before they start or after they leave) count as zero.

  3. Confirmed Time off in a category where the Removes from capacity switch is turned on removes its share of the day from the available hours. A full day removes all of them. A partial day, such as 50% time off, removes that share of the person's working hours. Time off in other categories, full-day or partial, keeps the day's hours available and counts as booked time off.

    1. An example of this could be a long-term leave, like parental leave.

  4. Public holidays reduce the day by the holiday's percentage (a half-day holiday removes half the hours).

  5. Otherwise, the day uses the Person's individual working hours if set, falling back to the Site's standard working hours.

Individual working hours always override the Site default. This is why a part-time Person changes a Project's effort totals: an unfilled Position planned against a Site's 40-hour week looks different once you assign someone who works 32 hours.

How time off interacts with planned work

Full-day and partial Time off behave differently where they meet an Allocation:

  • Full-day Time off ignores any work allocated over it, whatever its category. If a Person is allocated 100% to a Project for a week but takes that whole week off, Operating does not count the overlapping work, because they cannot deliver it. A tentative Allocation overlapping the time off is ignored too. When the Removes from capacity switch is turned on for the time off category, the days also leave the Person's available time.

  • Partial Time off takes its share out of the day, and the planned work fills the time that remains. For example, a Person is 50% off for a week and also has 100% of project work planned that week. The work fills the other half of each day, so the Project plans 4 hours a day on an 8-hour day.

    On the People timeline, the Person's total bar adds the Time off and the work together, so it reads 150%. The bar is not marked as overbooked, because Time off never counts toward overbooking.

    When the Person's confirmed Allocations add up to less than 100%, the Time off takes the free time first. On an 8-hour day with 50% Time off, an Allocation of 50% plans 4 hours, the same as an Allocation of 100%. A day is overbooked only when the confirmed Allocations alone add up to more than 100%.

To see days where work and Time off together come to more than 100%, turn on Highlight overlapping time off in your view options. The total bar then shows those days in orange.

A highlighted day is a prompt to look closer: is the Person really half-away every day, or away for the first half of the week and back for the second? Adjusting the Allocations to match reality removes the highlight.

Capacity is not utilization

Capacity and utilization both build on a Person's working hours, but they answer different questions and aren't the same number.

  • Capacity is a forward-looking planning view: how much of someone's available time is already booked.

  • Utilization measures what share of working time went to work (billable client work, by default). Its formula is configurable in Settings.

The two also treat time off differently:

  • Capacity counts time off as booked time.
  • Utilization keeps time off in its denominator by default, so time off lowers utilization unless a firm changes the formula to subtract it.

Time off in a time off category where the Removes from capacity switch is turned on is left out of available time in both, a partial day by its share. See How utilization is calculated in Operating.